6th Street East of Oak Street Lane Closures Starting April 21
6th Street SE will be undergoing utility work.
May 19: Project has been delayed due to weather. Continue to monitor Driver Alerts for updates.
Impacts
Beginning April 21
- Closed in the eastbound direction between Oak Street SE and the Maroon lot entrance.
Beginning April 28
- Closed in both directions between Oak Street SE and the Maroon lot entrance.
Detours
Vehicles
- Use Oak Street, University Avenue, and 23rd Avenue to detour around the closure.
- Parking in the Maroon Lot? Use 6th Street from 23rd Avenue to access the lot.
Transit
- The East Bank Circulator (120) and Campus Connector (121) will be on detour. Most stops will remain unchanged, except:
- The 120 and 121 bus stop at the Thompson Center for Environmental Management will be moved across 23rd Avenue SE.
- The 120 stop at the Center for Magnetic Resonance Research will be closed.
Maps
Vehicle detour
Transit detour